Task
|
People responsible
|
Expected Completion Date
|
Actual Completion Date
|
Status
|
Formulate research questions
|
Unmil (Tolga, Youngjoo)
|
9/27/2004
|
10/4/2004 (so, we're already late)
|
Done.
|
| Install Resource Manager on csdll.cs.tamu.edu |
Youngjoo |
10/6/2004 |
|
|
Discuss the modifications needed to the Resource Manager for the study
|
Youngjoo, Unmil
|
10/6/2004
|
|
|
IRB Documentation (forms, consent document, audio tape consent)
|
Tolga (Unmil, Youngjoo)
|
10/12/2004(?)
|
10/19/2004 (third draft)
|
Done.
|
Create Questionnaires (pre, during, and post-task questionnaires)
|
Unmil, Tolga, Youngjoo
|
10/12/2004(?) |
10/19/2004 (second draft)
|
Done.
|
Establish Experimental Protocol
|
Unmil, Tolga, Youngjoo
|
10/12/2004(?) |
10/15/2004 (second draft)
|
Done.
|
| User study Design
|
Unmil, Youngjoo, Tolga
|
10/12/2004(?) |
10/15/2004 (second draft)
|
Done.
|
Working prototype of the Resource Realizer
|
Unmil
|
11/15/2004 |
|
Postponed to December
|
Working prototype of the Resource Manager
|
Youngjoo
|
10/15/2004(?) |
|
|
| Apply for IRB Approval |
Tolga, Youngjoo (Unmil) |
10/15/2004(?) |
10/20/2004
|
Done
|
Setup database for saving data collected from the user study
|
Jeevan, Unmil
|
10/11/2004
|
10/19/2004 (first draft)
|
Working on final draft
|
Create pre- and post-task questionnaire Web pages
|
Jeevan
|
10/11/2004
|
|
|
Create task Web pages (pages that show pairs of images and receive user feedback)
|
Jeevan
|
10/25/2004
|
|
|
Create the set of images to be used for the study
|
Unmil, Jeevan
|
10/25/2004
|
|
|
Complete the system setup for user studies
|
Jeevan, Unmil
|
10/25/2004
|
|
|
Test the complete system setup with an "internal" user
|
Unmil, Jeevan
|
10/27/2004
|
|
|
| IRB Approval |
IRB (but, of course) |
10/22/2004(?) |
|
|
Advertise study and recruit users
|
Unmil, Tolga, Youngjoo
|
10/22-10/27/2004(?) |
|
|
Conduct user study
|
|
10/29 - 11/5/2004(?) |
|
|
Analyze data
|
|
|
|
|